David Lauter and Lisa Mascaro
Los Angeles Times
April 18, 2014
A further delay in the evaluation of the pipeline, which already has lasted more than five years, is necessary because of a Nebraska state court decision in February that invalidated part of the project’s route, the State Department said in a statement.
Shortly after the court ruling, administration officials had said the Nebraska case would not have an impact on their deliberations. But in the new statement, the State Department said federal agencies could not evaluate the pipeline’s impact until the “uncertainty created by the ongoing litigation” is resolved.